Realise the Shortcomings

Prasun K. Sengupta

The Indian Army (IA) continues to be beset with block obsolescence of military hardware in several niche areas of its principal combat arms, thereby affecting its war preparedness for even waging limited, high-intensity conventional warfare. The only tangible accretions in this decade have been in the arenas of tube and rocket artillery.

Indian Army testing the M-777 howitzer

For instance, the IA on November 9 last year formally inducted the BAE Systems-supplied M-777 ultra-lightweight 155mm/39-calibre field howitzer and the Hanwha-Techwin-supplied K-9 Vajra 155mm/52-cal tracked self-propelled howitzer into service. The IA took delivery of 10 of the 100 K-9s that it had ordered in mid-2016 at a cost of Rs 43.66 billion (USD600.4 million) at the IA’s Field Artillery Training Centre at Deolali in Maharashtra, western India.

The remaining 90 Vajras will be delivered by Larsen & Toubro to the IA by November 2020, with the first K-9 Regiment becoming operational last July. The IA has so far also inducted five M-777s, with another 25 units now being supplied directly to the IA along with Selex-built Laser Inertial Artillery Pointing Systems. The remaining 120 of a total of 145 M-777s ordered in 2016 for USD737 million, will be built at the BAE Systems/Mahindra Defence Assembly, Integration and Training (AIT) facility, with all deliveries being completed by mid-2021.

On April 8 last year, following eight years of laborious developmental work, the first six of 114 Dhanush-45 towed 155mm/45-cal field howitzers, each costing USD2 million, were delivered to the IA by the Jabalpur-based Gun Carriage Factory of the state-owned Ordnance Factory Board (OFB). The first 36 Dhanush-45s were due for delivery by last month, with another 48 to be delivered this year, with the remaining 48 to be delivered by the end of 2022. Presently, 81 percent of the Dhanush’s components are indigenously made, with the number expected to rise to 90 percent in subsequent production tranches.

Meanwhile, the Advanced Towed Artillery Gun System (ATAGS) project, initiated in 2013 for developing a homegrown, 18-tonne 155mm/52-cal towed howitzer, continues its developmental phase, with two competing designs being developed — one each by Kalyani Strategic Systems/Bharat Forge (G-2 prototype) and the TATA Aerospace & Defence (Tata A&D) Group (G-1 prototype). So far, 10 prototype units have been sanctioned. Following final selection of the lowest bidder, or L-1, the winner will be awarded a contract to build 100 of the 150 ATAGS (costing USD524 million), while the L-2 runner-up will be contracted for producing the remaining 50 under India’s first-ever public-private partnership (PPP) project in the defence production sector. The total requirement for ATAGs is pegged at 1,850 units. For the IA’s requirement for 814 155mm/52-cal mounted gun systems (MGS), the OFB is proposing a locally developed Dhanush-52 solution.

It was in March 2006 that the IA had placed a USD45 million contract with Tata A&D and Larsen

Subscribe To Force

Fuel Fearless Journalism with Your Yearly Subscription

SUBSCRIBE NOW

We don’t tell you how to do your job…
But we put the environment in which you do your job in perspective, so that when you step out you do so with the complete picture.